Kazakhstan plans to build Russian-border gas link by 2030
ASTANA. Nov 20 (Interfax) - Kazakhstan plans to start building new sections of the Saryarka trunk pipeline toward the Russian border in January 2028 and finish in December 2029, with the facilities due to enter service in 2030, according to documents published in the national environmental data bank.
The schedule is set out in an environmental impact report for the fourth revision of the Saryarka pipeline project, prepared by Elkon for AstanaGas KMG.
Construction will take 24 months, the report says. The new section will run 331.84 km through the Akmola region and 203.6 km through the North Kazakhstan region, along the Astana-Kokshetau-Petropavlovsk-Russian border route.
The project is split into three phases. The first covers the pipeline itself, an automated gas distribution station at Kokshetau, a repair and maintenance site, a workers' camp and an upgrade of the existing Astana maintenance site. The second adds pipeline facilities, a station at Petropavlovsk and a maintenance point. The third covers a compressor station at Kokshetau, a gas metering station at the Russian border and upgrades to existing pigging launch and receiving units on the operating Saryarka line in the Kyzylorda, Karaganda, Akmola and Ulytau regions.
The second and third phases are meant to raise the transmission system's capacity and bring Kazakh gas from western fields via Kyzylorda and Astana to Kokshetau, Petropavlovsk and other towns in the Akmola and North Kazakhstan regions, as well as to give access to Russian gas.
Kazakhstan and Russia have been working on the technical and commercial terms for the Ishim-Astana pipeline, a project to gasify northern Kazakhstan. The Kazakh government and Gazprom signed a strategic cooperation agreement in 2023 covering supplies, transportation and processing of natural gas, as well as exploration and production. The sides discussed building pipeline infrastructure with capacity of 45 billion cubic meters, of which 10 bcm was to go to gasifying northeastern Kazakhstan and 35 bcm to exports to China. In October 2025, Gazprom and Kazakhstan signed a memorandum on building the new Ishim-Astana trunk pipeline from Russia.
The Saryarka pipeline was commissioned in 2019, with the project's total cost estimated at 370 billion tenge. The first phase, running 1,061.3 km from Kyzylorda through Zhezkazgan and Karaganda to Astana, is complete.
AstanaGas KMG is a state project and infrastructure company set up to build and own trunk pipelines in central and northern Kazakhstan. Its shares are split evenly between the Samruk-Kazyna sovereign wealth fund and Orken Capital Fund, an investment fund owned by the Baiterek holding through Qazaqstan Investment Corporation.